September 23, 2024 Chungju Daehwa Mine – Project Progress Update
페이지 정보

본문
H-beam structural frames for the processing plant—previously purchased and refurbished—have been inspected, painted, and installed on the grading- and retaining-completed site.
Base plates and anchor bolts were installed beneath each structural column, and all structural connections were reinforced to ensure long-term operational safety.
Due to the high weight of installed processing equipment, hoisting capability is essential. Accordingly, a 15-ton hoist and gantry system have been installed and have passed all required safety inspections.