March 14, 2025 Chungju Daehwa Mine – Project Progress Update
페이지 정보

본문
Groundwater resources secured by well construction will be utilized to improve industrial water supply across the entire mine site, including the processing plant and waste-rock stockpile.
The waste-rock pile located adjacent to the road requires additional fill material to achieve uniform grade conditions suitable for pipe installation.
Under the prior approval conditions for the new Main Adit development (1,381㎡), an equivalent area (1,417㎡) of previously authorized land is required to be relinquished. Restoration works on the returned area are underway, including stone-retaining structures to protect slopes from erosion.
Soil and stone generated during ground preparation at the new Main Adit site are being effectively reused for restoration, foundation reinforcement, and fill operations.