March 27, 2025 Chungju Daehwa Mine – Project Progress Update
페이지 정보

본문
Heavy equipment was mobilized to the newly
approved 1,381㎡ Main Adit site to conduct slope
trimming and ground compaction prior to excavation.
Soil generated during this process is being used as fill for the waste-rock
stockpile, while stone materials are utilized for restoration and retaining
wall works on the previously returned site.
As part of the restoration, the waste-rock site—where
the well construction was completed—requires proper ground preparation for
pipeline installation.
The stone retaining wall work also plays a critical role in preventing slope
erosion and will support upcoming slope-greening work using seed-spray methods