April 17, 2025 Chungju Daehwa Mine – Project Progress Update
페이지 정보

본문
The vibrating feeder (Vibrating Feeder)
previously stored at the waste-rock site has been relocated to the processing
plant for overhaul and installation.
Fabrication of the base frame for the first cone crusher has been completed,
and overhaul work has begun.
At the Main Adit site, ten excavators
operated over 15 days to cut and level the slope, preparing the tunnel
entrance.
Upon completion of this groundwork, detailed design drawings for the tunneling
direction and working face will be submitted to the Central Mine Safety Office
for approval before excavation begins.