May 16, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 32회 작성일 25-10-28 09:46

본문


The overhauled primary cone crusher (Con Crusher) was successfully installed on its custom-built support frame.

As the machine itself weighs over 50 tons, a crane was required to position the equipment, as internal hoisting alone was insufficient.

Exterior panel installation continued, including work on both primary entrance façades of the processing plant.