August 19, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 30회 작성일 25-10-28 09:58

본문

Formwork was removed from three previously cast concrete foundation areas, including:

    1. Aggregate discharge facility pad

    2. Processing plant water tank foundation

    3. Waste-rock stockpile groundwater well pad

The water tank at the crusher loading area will be uprighted and connected shortly.
To prevent winter freezing, the well pad was reinforced using a concrete enclosure and an additional protective steel container.

A vibrating feeder for the aggregate line has been installed on the prepared concrete pad, and overhaul inspections have commenced