April 16, 2024 Chungju Daehwa Mine – Project Progress Update
페이지 정보

본문
Following the conclusion of approved timber-clearing activities on the 15,649㎡ processing facility site, the Company commenced ground-leveling operations.
Due to the scale of the facility and the heavy industrial equipment to be installed, extensive leveling and ground reinforcement is required to ensure long-term structural integrity. Additional slope stability measures are being implemented to prevent soil erosion and safeguard the future operation of the processing plant.