June 18, 2024 Chungju Daehwa Mine – Project Progress Update
페이지 정보

본문
Concrete retaining-wall blocks have been installed on the slopes of the processing plant and waste-rock site. Reinforced-soil work has been completed on each graded bench where ground improvement was finalized.
To ensure proper drainage, drainage piping has been installed along the perimeter of the site and terrace edges. Insulation material has also been applied to the plant floor foundation.