December 10, 2024 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 34회 작성일 25-10-27 18:19

본문


The primary jaw crusher, with a processing capacity of 100–150 tons per hour, has been securely installed with reinforced foundation support due to significant ground forces generated during crushing operations.

As the mine currently has only one portal (South Adit), the Company has applied for temporary mountain-use authorization to construct an additional portal (Main Adit), which will connect to the existing adit to improve production efficiency and site safety.

Upon receiving the approval notice, the Company commenced timber clearing within the authorized area and transported felled pine trees externally under an official removal certificate issued by the Forest Authority.