April 8, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 31회 작성일 25-10-28 09:39

본문


During the previous winter, severe freezing caused the collapse of existing water pipelines, halting several construction activities across the site.
The ongoing water pipeline installation aims to prevent future supply interruptions during winter operations.

Since the waste-rock stockpile is located at the lowest elevation, the trenching work proceeds upward along the slope while laying pipes and cables. Due to safety concerns, construction is being carried out with heightened caution and step-by-step inspection.