April 17, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 29회 작성일 25-10-28 09:42

본문


The vibrating feeder (Vibrating Feeder) previously stored at the waste-rock site has been relocated to the processing plant for overhaul and installation.
Fabrication of the base frame for the first cone crusher has been completed, and overhaul work has begun.

At the Main Adit site, ten excavators operated over 15 days to cut and level the slope, preparing the tunnel entrance.
Upon completion of this groundwork, detailed design drawings for the tunneling direction and working face will be submitted to the Central Mine Safety Office for approval before excavation begins.