April 22, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 31회 작성일 25-10-28 09:43

본문


The overhaul of the relocated vibrating feeder and its support frame has been completed.
Overhaul and frame fabrication for the primary cone crusher are now in progress.

Among several belt conveyors stored at the waste-rock site, those designated to transport crushed ore from the jaw crusher to the primary cone crusher have been selected, inspected, and moved to the processing plant.
Maintenance work including roller replacement, rubber mat inspection, and steel mesh (EX-METAL) installation is underway.

In compliance with restoration obligations, approximately 110 fir trees (0.3m) were planted in the designated reforestation zone, and slope seeding results will be reported to the Forest Authority by the April 30, 2025 deadline.