April 24, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 28회 작성일 25-10-28 09:43

본문


Exterior wall paneling for the processing plant has resumed.
A 50-ton crane was mobilized to install the side wall panels, followed by attachment of C-channel framing to support the upcoming roof panel installation.

Additional H-beam columns were erected and secured at the front and rear sections of the facility, where main access doors will be installed.