April 30, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 29회 작성일 25-10-28 09:44

본문


Due to the incline and cut-slope position of the processing plant, a major retaining wall had been installed to prevent landslides. The wall previously showed slight tilting toward the plant and was recently reinforced for additional safety.

The level ground behind the retaining wall will serve as the loading and unloading zone for 15-ton dump trucks transporting ore into the Jaw Crusher hopper. To increase structural stability, additional gravel was transported to the area and compacted.

Multiple belt conveyors will be installed to support ore transfer between the crushing and screening stages inside the processing plant. Recently, a set of belt conveyors was purchased at competitive pricing and delivered to the site for installation.