July 2, 2024 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 24회 작성일 25-10-27 18:09

본문


Concrete placement for the access route to the processing plant and waste-rock site has been completed. Steel structural components and frames for the processing facility have been transported and staged at the completed civil construction areas. Additional equipment and materials are being gradually mobilized.

Upon completion of the upcoming monsoon season, which is expected to last approximately one month, the Company will commence full-scale processing plant installation works.