August 14, 2024 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 26회 작성일 25-10-27 18:10

본문


Following approximately one month of monsoon conditions, construction of the processing plant facility resumed in late July.
During the monsoon period, the Company completed procurement of remaining auxiliary components required for plant installation and secured major equipment for internal installation post-construction. These items were transported to the waste-rock stockpile area for staging.

As the processing plant is being constructed on a slope of approximately 16 degrees that was cut and developed into a flat work platform, landslide and slope failure risks remain a critical concern. To mitigate such risks, the Company prioritized securing slope stability ahead of full facility operation.

Slope areas outside the processing plant were reinforced with concrete retaining blocks and engineered backfill. On the uphill side, additional retaining wall works were executed to ensure safe working conditions for on-site personnel.