September 23, 2024 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 27회 작성일 25-10-27 18:12

본문


H-beam structural frames for the processing plant—previously purchased and refurbished—have been inspected, painted, and installed on the grading- and retaining-completed site.

Base plates and anchor bolts were installed beneath each structural column, and all structural connections were reinforced to ensure long-term operational safety.

Due to the high weight of installed processing equipment, hoisting capability is essential. Accordingly, a 15-ton hoist and gantry system have been installed and have passed all required safety inspections.