March 27, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 31회 작성일 25-10-28 09:37

본문


Heavy equipment was mobilized to the newly approved 1,381 Main Adit site to conduct slope trimming and ground compaction prior to excavation.
Soil generated during this process is being used as fill for the waste-rock stockpile, while stone materials are utilized for restoration and retaining wall works on the previously returned site.

As part of the restoration, the waste-rock site—where the well construction was completed—requires proper ground preparation for pipeline installation.
The stone retaining wall work also plays a critical role in preventing slope erosion and will support upcoming slope-greening work using seed-spray methods