April 4, 2025 Chungju Daehwa Mine – Project Progress Update

페이지 정보

profile_image
작성자 최고관리자
댓글 0건 조회 30회 작성일 25-10-28 09:38

본문


Groundwater well construction successfully secured approximately 50 tons of daily water supply.
To distribute this water throughout the mine—including lodging, dining facilities, offices, and the processing plant—pipelines and electrical conduits are being installed.

Starting from the leveled waste-rock stockpile, trenches 1.2 meters deep are being excavated to lay 32mm water pipes and electrical conduits.
These lines will connect the pump station and transformer to ensure full electrical and water supply integration across the site.