April 22, 2025 Chungju Daehwa Mine – Project Progress Update
페이지 정보

본문
The overhaul of the relocated vibrating
feeder and its support frame has been completed.
Overhaul and frame fabrication for the primary cone crusher are now in
progress.
Among several belt conveyors stored at the
waste-rock site, those designated to transport crushed ore from the jaw crusher
to the primary cone crusher have been selected, inspected, and moved to the
processing plant.
Maintenance work including roller replacement, rubber mat inspection, and steel
mesh (EX-METAL) installation is underway.
In compliance with restoration obligations, approximately 110 fir trees (0.3m) were planted in the designated reforestation zone, and slope seeding results will be reported to the Forest Authority by the April 30, 2025 deadline.