June 13, 2025 Chungju Daehwa Mine – Project Progress Update
페이지 정보

본문
Painting of the fully installed and
overhauled primary cone crusher has been completed.
A belt conveyor was installed to interconnect the jaw crusher and vibrating
feeder, and rubber belts will be installed ahead of testing operations.
For the restored return area (1,417㎡), slope stabilization measures were finalized with installation of coir matting over seeded areas, followed by additional soil-spraying and re-seeding to support vegetation.